HPP Golling - hydraulich scale model test
Abstract
VERBUND Hydro Power GmbH (VHP) is planning the construction and operation of the Golling power plant (KW Golling) as a diversion power plant on the Salzach. For this purpose, a sectional model on a scale of 1:20 is constructed in order to check the capacity of the weir system and the functionality of the stilling basin and, if necessary, to optimize the design. Finally, the risk of clogging of the weir system is to be examined and, if necessary, reduced by design measures.
Project staff
Christine Sindelar
Priv.-Doz. Mag. Dipl.-Ing. Dr.techn. Christine Sindelar
christine.sindelar@boku.ac.at
Tel: +43 1 47654-81944
Project Leader
01.04.2024 - 30.09.2025
Matthias Buchinger
Dipl.-Ing. Matthias Buchinger
matthias.buchinger@boku.ac.at
Tel: +43 1 47654-81940
Project Staff
01.04.2024 - 30.09.2025
Dominik Worf
Dipl.-Ing. Dominik Worf
dominik.worf@boku.ac.at
Tel: +43 1 47654-81937
Project Staff
01.09.2024 - 31.03.2025